29/08/2026
work Done :
Carparking column 2 No De shuttering work completed.
Sump Mate concrete sides deshuttering work completed.
Septic tank Brick work 90 percentage Covered.
Sump Rcc wall outer sides Brick work under work progress.
Curing work and etc