24/07/2026
Leap Suites Construction Update ๐๏ธ
The second floor slab successfully completed. Steelwork, Mechanical Electrical and Plumbing works were thoroughly inspected to give room for the slab casting.
There was transition from hollow-pots slab to solid slab in thislevel onwards.
Third Floor Slab (CurrentActivity)
Current progress is focused on Third-floorformwork.
The project team is increasing workforce coordination and site productivity to improve progress and regain schedule performance.
Call: 0702655166 to book a unit or schedule a site visit.