Leap Suites Construction Update ๐Ÿ—๏ธThe second floor slab successfully completed. Steelwork, Mechanical Electrical and Plu...
24/07/2026

Leap Suites Construction Update ๐Ÿ—๏ธ
The second floor slab successfully completed. Steelwork, Mechanical Electrical and Plumbing works were thoroughly inspected to give room for the slab casting.
There was transition from hollow-pots slab to solid slab in thislevel onwards.
Third Floor Slab (CurrentActivity)
Current progress is focused on Third-floorformwork.
The project team is increasing workforce coordination and site productivity to improve progress and regain schedule performance.
Call: 0702655166 to book a unit or schedule a site visit.
๐Ÿ“ Leap Suites
๐Ÿ”จ More site updates coming soon

Leap Suites Construction Update ๐Ÿ—๏ธThe First Floor Slab Works were substantially completed, including:- Hollow Pot Arrang...
24/06/2026

Leap Suites Construction Update ๐Ÿ—๏ธ
The First Floor Slab Works were substantially completed, including:
- Hollow Pot Arrangement.
- Reinforcement fixing.
- Formwork Preparation
- Mechanical, Electrical and Plumbing (MEP) installations.
- Slab Concreting.
Current progress is focused on the Second-floor Slab, where:
-Formwork Installation is approximately 40% complete.
-Steel Reinforcement works are scheduled to commence
-Mechanical, Electrical and Plumbing(MEP), works will be carried out prior to slab concreting.
Call: 0702655166 to book a unit or schedule a site visit.
๐Ÿ“ Leap Suites
๐Ÿ”จ More site updates coming soon

01/06/2026
Leap Suites Construction Update ๐Ÿ—๏ธThe upper ground parking slab workswere substantially completed, including:-Hollow pot...
22/05/2026

Leap Suites Construction Update ๐Ÿ—๏ธ
The upper ground parking slab workswere substantially completed, including:
-Hollow pot arrangement
-Reinforcement fixing
-Coordination of Mechanical, Electrical & Plumbing (MEP) installations prior to casting.
First Floor Slab Works (Current Activity)
Current progress is focused on the first-floor slab, where:
-Formwork installation is approximately 90% complete
-Reinforcement preparation is ongoing.
-Site coordination for upcoming slab activities is in progress.
Call: 0702655166 to book a unit or schedule a site visit.
๐Ÿ“ Leap Suites
๐Ÿ”จ More site updates coming soon

Address

P. O. BOX 00600-33233
Nakuru
254

Opening Hours

Monday 08:00 - 17:00
Tuesday 08:00 - 17:00
Wednesday 08:00 - 17:00
Thursday 08:00 - 17:00
Friday 08:00 - 17:00

Telephone

+254702655166

Alerts

Be the first to know and let us send you an email when Leap Suites posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Leap Suites:

Shortcuts

Share

Category