30/03/2021
🚧Construction Updates🚧
Urban Village Phase 2 bored pile foundation works and the lateral support system is completed. Current construction stage undergoing excavation of soil, pile head cutting and rectification, and basement lean concrete. The next stage works for the basement construction include waterproofing works, pile cap, and basement structural construction.
Please stay tuned for the next updates.