12/09/2026
BOND STREET
DATE 10-SEP-2026
* Tower A & B: Aluminum window installation work at the 7th typical floor. New electric power supply meter installation. Basement ramp cleaning for PCC work.
* Tower B: Elevation painting work.
* Tower C: Cement shifting for plaster work. 3rd typical floor plaster work. 7th typical floor Part B slab shuttering work. Remaining Part C column pouring work at the 7th typical floor.
* Tower D: Rooftop block making work.
* Tower C & D: 12 mm glass panel fixing at Shops No. 53, 63, 64 & 65.
* Tower E: 7th typical floor Part B slab shuttering work. Bond Street Hayat Builders and Developers