06/09/2026
CONSTRUCTION UPDATE | Kew Palm House
We’re pleased to share the latest progress at Kew Palm House. Last Saturday marked a key milestone with three excavators making fast progress, and the concrete pour to pad footings of building B now complete. The team is on track to finalise excavation of Building A by the end of September.
Construction is progressing steadily, with move in anticipated for late 2027.
Stay tuned for more updates as we build towards this exciting next chapter for Kew Palm House.