25/10/2023
Construction update - Cubi Lonsdale
This month we had slabs laid in warehouses 30 to 33.
Currently panels for warehouses 17 to 22 are being erected as well as base prep for warehouses 11 to 16.
Finishing out the month we will see base prep and footings dug for warehouses 1 to 10 and structural steel arriving on site.