03/10/2023
We are delighted to announce that we are finally at full capacity with 105-110 contractors onsite daily across multiple trades.
It is exciting to finally have the momentum we have been waiting for, after so many months of sporadic attendance from both subcontractors and staffing when GCB was managing the site.
We are pushing full steam ahead now without compromising on delivering a quality project next year.
Now that we are the builders, you can enjoy specific and real-time program updates as outlined below:
• Get ready for the big reveal as the scaffolding drop begins from the top down
• Joinery has been completed from levels 1- 5 with level 6 being installed this week
• Wardrobe & shower screen contracts have now been awarded, with site measurement underway up to level 7
• Stone installation commenced today with measuring completed up to level 5
• Balustrading posts are in with the glass install starting towards the end of the week on level 15 and working down
• Painters are working in and around the external scaffold exterior and are also working up the internal of the building
• All other trades are tracking well including electrical, plumbing, waterproofing, tiling, and mechanical
We have a strong team in place and are on track to deliver View in the first half of 2024. We will update you with a more accurate timeframe as we move closer to completed works.
We want to thank you as our valued purchaser, for your patience and support as we have built our construction team in the past months. We truly believe it will be worth the wait.