12/06/2026
SYMPHONY 7 Case Study Update:
Even though I've been in Jakarta, Indonesia, for the past few weeks, the beauty of a unique team is that you are able to keep things rolling via WhatsApp messaging and videos.
Communication doesn't stop; progress doesn't stop. It's pretty much instant. Things keep rolling and that's important when you've got a unique team around you.
With Symphony 7 we are progressing now to stages where we are doing the external tiling in the pool and barbecue area.
The electrical fit out is happening.
Notice the curved stone under the bench on the left-hand side that was supposed to be a non-stone element.
The stone supplier, because of the volume of work we give them, added matching stone as a little value add for us 😀
UPDATE MASTER WIR: we have expanded the walk-in robe space, we've gone from a 760 mm walkway between the robes to a 1 m walkway.
All the plastering is done and we have prepped ready for our master painter.
So, exciting times ahead despite winter being upon us. Everyone is able to focus and adjust work accordingly.
Looking forward to landing back in Melbourne next Monday and going there to see it for myself.