25/11/2025
THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Work is racing ahead with the final slab to be poured this coming week. The plan is to have the roofto...
23/11/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ
Work is racing ahead with the final slab to be poured this coming week. The plan is to have the rooftop all waterproofed by the Christmas break for the fitout to commence straight after the break.

https://huxleyandparks.com.au/thetalle

Construction Update 5 ๐Ÿ  - Week 19 - Nov 20th
๐Ÿ‘‰Level 2 concrete slab poured and blockwork complete.
๐Ÿ‘‰Level 3 concrete slab formwork complete and pour scheduled for next week.
๐Ÿ‘‰Waterproofing applied to ground floor and level 1 windows and doors
๐Ÿ‘‰Tiles and plasterboard deliveries start next week

Construction thanks to .






04/11/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ
Meet the developer.
Construction thanks to .





The Talle's website is now live! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Check out the new site and renders of the development. Four premium residences c...
08/10/2025

The Talle's website is now live! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ

Check out the new site and renders of the development. Four premium residences coming to the market very soon.

https://huxleyandparks.com.au/thetalle






When you travel to site for an inspection, catchup with the builder and to create some media content and the pilot does ...
25/09/2025

When you travel to site for an inspection, catchup with the builder and to create some media content and the pilot does a fly by The Talle on the way in to land ๐Ÿ›ฌ๐Ÿ ๐Ÿ‘Œ

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Significant progress was again made onsite despite a few weather disruptions. Engineering sign-off was...
20/09/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ
Significant progress was again made onsite despite a few weather disruptions. Engineering sign-off was received on the ground floor columns and block work.

Construction Update 4 ๐Ÿ  - Week 6 - Aug 22nd
๐Ÿ‘‰Structural steel and formwork for columns.
๐Ÿ‘‰Formwork shutters for ground floor garage columns installed and signed off.
๐Ÿ‘‰Termite protection on lift shafts and column formwork complete.
๐Ÿ‘‰Ground floor blockwork core filled and completed.

Construction thanks to .






THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Construction powered on over the fortnight with the steel setup for the footings completed, the concre...
29/08/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ
Construction powered on over the fortnight with the steel setup for the footings completed, the concrete strip footings poured, ground slab preparation was completed and the ground slab was also poured.

Construction Update 3 ๐Ÿ  - Week 4
๐Ÿ‘‰Concrete strip footings poured.
๐Ÿ‘‰Ground slab steel installation completed.
๐Ÿ‘‰Ground slab poured.
๐Ÿ‘‰Termite protection installed.

Construction thanks to .






THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Currently for sale off market. Don't miss your opportunity before these residences are on market! Due ...
26/07/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ
Currently for sale off market. Don't miss your opportunity before these residences are on market! Due for completion June 2026.

Construction Update 2 ๐Ÿ 
๐Ÿ‘‰Excavation of strip footings for Unit 4 complete
๐Ÿ‘‰Screw piers were cut down to the required height.
๐Ÿ‘‰10 truckloads of soil removed from site.
๐Ÿ‘‰Footing steel delivered

Construction thanks to .






THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ Construction Update 1 ๐Ÿ ๐Ÿ‘‰Bio-retention basin installed.๐Ÿ‘‰Screw pier installation completed. Some to a de...
19/07/2025

THE TALLE! ๐Ÿฅ‚๐ŸŒด๐Ÿ„โ€โ™‚๏ธ

Construction Update 1 ๐Ÿ 
๐Ÿ‘‰Bio-retention basin installed.
๐Ÿ‘‰Screw pier installation completed. Some to a depth of 9m!
๐Ÿ‘‰Underground services have been completed, ready for footings.

Construction thanks to .






BANG! ๐Ÿ’ฅIt's been a while to get to this point but things are now moving along quickly. Formal approval has been received...
29/05/2025

BANG! ๐Ÿ’ฅIt's been a while to get to this point but things are now moving along quickly. Formal approval has been received this week for funding ๐Ÿ’ฐ so it's full steam ahead! ๐Ÿš‚

Thanks to .by.numbers and for getting us to this point.

Let the building begin.