12/10/2026
A massive effort from the crew on site this month. Lots happening beneath the surface at Paradiso Place!
We've hit 71% completion on our 49 diaphragm wall panels and 112 foundation piles—each driven 45 metres below ground and bored a further 5 metres into solid bedrock.
Follow us and stay tuned for regular construction updates!