Mayrin Group

Mayrin Group Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Mayrin Group, Property developer, 3/33 York Street, Sydney.

Merry Christmas and Happy New Year. From all of us, thank you for being part of our year. May the next one meet you with...
24/12/2025

Merry Christmas and Happy New Year. From all of us, thank you for being part of our year. May the next one meet you with warmth, possibility, and a little sparkle.

We‘re excited to share that The Archwood Residences has been named a finalist in the 2025 UDIA NSW Awards for Excellence...
10/07/2025

We‘re excited to share that The Archwood Residences has been named a finalist in the 2025 UDIA NSW Awards for Excellence, under the Excellence in Medium Density Development category.

This follows our recent Highly Commended Award at the Urban Taskforce Development Excellence Awards and a finalist spot in The Urban Developer Awards – a continued recognition of the vision behind this project.

Located in Roseville, The Archwood Residences brings together timeless design, sustainable materials, and a strong sense of community across 42 low-rise townhouses. From locally sourced sandstone to accessible living and native landscaping, every detail reflects our commitment to quality and liveability.

Huge thanks to our amazing team and our collaborators at Growthbuilt and DKO for helping bring this vision to life.

We're excited to share that The Archwood Residences has been named a finalist in the 2025 UDIA NSW Awards for Excellence...
10/07/2025

We're excited to share that The Archwood Residences has been named a finalist in the 2025 UDIA NSW Awards for Excellence, under the Excellence in Medium Density Development category.

This follows our recent Highly Commended Award at the Urban Taskforce Development Excellence Awards and a finalist spot in The Urban Developer Awards – a continued recognition of the vision behind this project.

Located in Roseville, The Archwood Residences brings together timeless design, sustainable materials, and a strong sense of community across 42 low-rise townhouses. From locally sourced sandstone to accessible living and native landscaping, every detail reflects our commitment to quality and liveability.

Huge thanks to our amazing team and our collaborators at Growthbuilt and DKO for helping bring this vision to life.

The Archwood Residences has been recognised with a Highly Commended Award for Low Rise Residential Development at the pr...
03/07/2025

The Archwood Residences has been recognised with a Highly Commended Award for Low Rise Residential Development at the prestigious 2025 Urban Taskforce Development Excellence Awards.

This honour celebrates the project’s commitment to quality design, sustainability, and creating a new benchmark for low-density living on Sydney’s Upper North Shore. Located just 11km from the CBD, The Archwood Residences features thoughtfully designed townhomes, private lifts in selected residences, generous use of local sandstone, and native landscaping that blends seamlessly with the environment.

We’re proud to see our vision for modern, sustainable living recognised at this level.

Read more: https://www.urbantaskforce.com.au/development-excellence-awards-2025/

May the Year of the Snake Bring You Prosperity, Growth, and New Adventures!
28/01/2025

May the Year of the Snake Bring You Prosperity, Growth, and New Adventures!

24/12/2024

Shine Bright This Christmas and Set Sail into the New Year. Wishing you a joyful holiday season!

We are delighted to announce that, thanks to the dedicated efforts of our project team, construction on The Archwood Res...
28/11/2024

We are delighted to announce that, thanks to the dedicated efforts of our project team, construction on The Archwood Residences is progressing seamlessly. Buildings C, D, E, F, and G are now fully completed, while Buildings A and B are in the final stages of cleaning and finishing touches.

Progress on Buildings A and B:
• Sandstone work: Complete
• Mechanical assembly: Complete
• Pipework installation: Complete
• Electrical installation (including lighting): Complete
• Mechanical equipment installation: Complete
• Wooden flooring: Complete
• Indoor tiling and sidewalk paving: Complete

With Buildings C, D, E, F, and G finished, we are approaching the successful completion of the entire project.

Experience the refined beauty of The Archwood Residences. Our showroom is now open—book your private tour today by calling 1800 09 33 55.

Mayrin Group Wishes You and Your Family a Mid-Autumn of Peace, Joy and Moonlit Memories.
17/09/2024

Mayrin Group Wishes You and Your Family a Mid-Autumn of Peace, Joy and Moonlit Memories.

We are excited to share the latest construction updates for The Archwood Residences. As of September 2024, we have made ...
06/09/2024

We are excited to share the latest construction updates for The Archwood Residences. As of September 2024, we have made significant progress in each block, with all construction moving forward seamlessly.

Block A/B
• Sandstone work: 80% complete
• Mechanical fit off: 100% complete
• Plumbing fit off: 95% complete (except Lot 1)
• Electrical fit off: 95% complete
• Mechanical systems: 95% complete (except Lot 1)
• Timber flooring: 90% complete
• Internal tiling: 100% complete
• External tiling: 15% complete

Block C
• Final cleaning: 100% complete
• Courtyard paving: 100% complete

Block D & G
• Wet area tiling: 100% complete
• Pendant lighting: 100% complete
• Electrical fit off: 100% complete
• Plumbing fit off: 100% complete

Block E & F
• Tiling: 100% complete
• Mechanical systems: 100% complete
• Electrical commissioning: 100% complete
• Plumbing fit off (Blocks F and E): 100% complete
• Timber flooring: 100% complete (except basement)

Discover the elegance of The Archwood Residences—our showroom is now open. Secure your private tour today by calling 1800 171 188.

We‘re excited to share the latest construction progress for The Archwood Residences. As of Jun 2024, we have completed t...
01/07/2024

We‘re excited to share the latest construction progress for The Archwood Residences.

As of Jun 2024, we have completed the following work in each block:

Block A & B
- All service rough-ins are completed.
- Internal tiling is finished.
- Kitchen installation is 70% complete.
- Door installation is 95% complete.

Block C
- All service fit-offs are done.
- FF&E is completed.
- Planters and patio waterproofing are finished.
- Fencing is 70% complete.

Block D & G
- Tiling is complete.
- Kitchen installation is 95% complete.
- Door installation is 95% complete.
- Windows installation, façade works, and brickwork are finalized.
- Waterproofing to planters is completed.

Block E
- Electrical, hydraulic, and mechanical works are 95% complete.
- FF&E is 90% complete.
- Façade fit-off and planter brickwork are finished.

Block F
- Joinery work is completed.
- Electrical is 90% complete.
- Hydraulic and mechanical services are completed.
- FF&E is 90% complete.
- Planter brickwork is finished.

Stay tuned for more updates as we continue to make significant progress!

Architecture

We are delighted to share the latest construction updates on The Archwood Residences townhouses. The construction progre...
07/06/2024

We are delighted to share the latest construction updates on The Archwood Residences townhouses. The construction progress is going beautifully this month.

As of May 2024, we have completed the following work in each block:

Block AB –
Internal Sheeting is 90% complete
Façade Brickwork is complete
Windows installation is 95% complete
External Cladding is complete

Block C –
Electrical, Hydraulic, Mechanical Services Fit-Off is 90% complete
Fire services is complete
Flooring, Stone Tops, Door Installation is complete
FF&E is 90% complete
Scaffold strip and Brickwork is complete
Stone cladding is 95% complete
Irrigation is complete
Planters waterproofing is complete

Block D & G –
Internal tiling is nearly complete
Kitchens installation is 80% complete
Door Installation is 80% complete
Fire service is complete
Windows installation is 90% complete
Façade Works and fit-off is 80% complete
Scaffold strip is complete

Block E –
Internal flooring is complete
Internal tiling is 98% complete
Kitchen installation is 60% complete
Door installation is complete
Fire service is complete
Scaffold strip is complete
Façade fit-off is 80% complete
Planter brickwork is 80% complete

Block F –
Internal flooring, tiling, door installation is complete
Joinery with stone tops is 75% complete
Electrical and mechanical services fit-off is 70% complete
Hydraulic Services fit-off is 80% complete
Fire service is complete
Scaffold strip, Façade Fit-Off: Complete
Planter brickwork is 80% complete

Thank you for your continued support as we make significant strides towards the completion of The Archwood Residences townhouses. Stay tuned for more updates next month!

For more information, you can visit thearchwood.com.au or call 1800 171 118.

Happy Mother‘s Day!
11/05/2024

Happy Mother‘s Day!

Address

3/33 York Street
Sydney, NSW
2000

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

+61280689698

Alerts

Be the first to know and let us send you an email when Mayrin Group posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Mayrin Group:

Featured

Share