07/02/2023
58 Capricon road Truganina.
10 Townhouses project update:
Fixing Completed. 70% Paint work completed. Cabinets and Tiles installed.
Moving forward to pouring Concrete and starting landscaping in 3 weeks.
2 more months to complete this project.