Day 17 - Windsor Park Field of Play Redevelopment Another very productive day onsite with just over 9000m2 of sand slit ...
21/11/2024

Day 17 - Windsor Park Field of Play Redevelopment

Another very productive day onsite with just over 9000m2 of sand slit secondary drainage installed by the team 👏🏼

21/11/2024

Windsor Park Field of Play Redevelopment ~ Like poetry in motion our team installed 4000m of ag drains in the field of play as part of a fully integrated drainage system. West Tamar Council SPORTENG AFL Tasmania

Day 11 - Windsor Park Field of Play Redevelopment One of the most critical components to a surface redevelopment is the ...
14/11/2024

Day 11 - Windsor Park Field of Play Redevelopment

One of the most critical components to a surface redevelopment is the growing medium or rootzone material used.

Our design for this project incorporates 4500 tonne of our very own premium sand growing medium which blended with some secret herbs and spices for turf health provides a fantastic rootzone but just as importantly is also plays a pivotal role in the integrated drainage system combining with the ag-drains and sand slits to provide an all weather surface catering for Tasmania’s harshest winter rainfall events.

Our amazing sand mine & transport team have delivered just over 3000t of the 4500t required.

Day 7 ~ Windsor Park Field of Play Redevelopment.Another fantastic day by the team today with plenty of action onsite on...
07/11/2024

Day 7 ~ Windsor Park Field of Play Redevelopment.

Another fantastic day by the team today with plenty of action onsite on multiple fronts;
- completion of the perimeter kerb
- installation of electrical & coms pits
- irrigation trenching complete
- irrigation ring main install started
- excavation for light pole footings

Couldn’t be prouder of each and every one of our employees that turn up every day and deliver a solid days work 👷🏻‍♀️👷🏼‍♀️

Day 4 - Windsor ParkGreat progress by the team this week.Next weeks tasks;~ complete concrete kerb~ install electrical c...
31/10/2024

Day 4 - Windsor Park

Great progress by the team this week.

Next weeks tasks;
~ complete concrete kerb
~ install electrical conduits
~ install irrigation system
~ start light tower footings

Day 3 - Windsor Park Field of Play Redevelopment.Turf Stripping complete ✅20,000m2 in under 20 hours thanks to the great...
30/10/2024

Day 3 - Windsor Park Field of Play Redevelopment.

Turf Stripping complete ✅
20,000m2 in under 20 hours thanks to the great effort of our team & specialised turf equipment.

Day 2 ~ Windsor Park Field of Play RedevelopmentTurf stripping continuing + earthworks underway. The key to any project ...
29/10/2024

Day 2 ~ Windsor Park Field of Play Redevelopment

Turf stripping continuing + earthworks underway.

The key to any project is planning and the team have hit the ground running and on track to achieve this week’s targets ✅

Legana Primary School new oval growing in nicely ☘️🌱 Nothing more satisfying than contributing to make positive changes ...
18/06/2024

Legana Primary School new oval growing in nicely ☘️🌱

Nothing more satisfying than contributing to make positive changes in the community.
West Tamar Council AFL Tasmania

Great to see the progress of our new school from this aerial shot taken by Nigel from The Baker Group.

Later this week we will be sharing some photos from the next site visit - remember to share our page to your family and friends :)

We are very proud to support this great club. 🙌🏼
05/06/2024

We are very proud to support this great club. 🙌🏼

💙⚡️

Not even 12 months after being completed the George Town Football Club & George Town Council have been granted the Reliv...
01/03/2024

Not even 12 months after being completed the George Town Football Club & George Town Council have been granted the Relive the Rivalry game for 2024, what a great outcome!

Designed & Constructed by The Baker Group in 2022 in conjunction with SPORTENG the ground is now regarded as one of the best AFL Tasmania fields of play in the state.

Can’t wait to watch all the legends give it the thumbs up 👍🏼🏈

Congratulations on 30 great years IBP 👏🏼Reciprocal trade is important in any industry. We are extremely proud to not onl...
06/06/2023

Congratulations on 30 great years IBP 👏🏼

Reciprocal trade is important in any industry. We are extremely proud to not only be the sand supplier for the last 15 years but also a proud purchaser of blocks and pavers from Island Block & Paving over the last 30 years.

We are heading into our 30th year in business at Island Block & Paving! Join us as we kick off our “Meet the Team” series, where we introduce you to the individuals who have been the driving force behind Island Block & Paving.

We are starting off the series with Phil Thurlow, our Managing Director. With over 35 years of experience in the building industry, Phil’s knowledge and vision has helped shape Island Block & Paving over the years. Stay tuned as we continue to introduce you to the rest of the team over the next few months!

Address

Western Junction, TAS

Alerts

Be the first to know and let us send you an email when The Baker Group posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to The Baker Group:

Share