18/01/2023
JANUARY 2023 UPDATE
As we enter into the beginning of 2023, we have gotten further updates around the progress of the civil works at Ridge Park Estate.
The Developer has confirmed that the Sewer and Stormwater works will be finalised in the coming weeks. Following this, the electrical work will commence with is which is anticipated for mid this month. Once these works are underway, they will be completing the retaining walls.
The last large portion of the civil works will be all the roadworks, including the curb and guttering. It has been estimated that this portion of the work will take roughly two and a half months to complete.
With these timeframes in mind, the construction program predicts the completion to be in April 2023.