11/05/2026
When ATB Placeβs South Tower was under construction in 1969, the Alberta Business Journal estimated it would contain approximately 40,000 cubic yards of concrete. Thatβs enough to build a sidewalk from Edmonton to Red Deer, with about 50 kilometres left over, assuming a width of 1.5 metres and a thickness of 10 centimetres.
Concrete was only part of what went into the tower, originally known as the AGT Tower. The project also called for 2,700 tons of reinforcing steel and 1,800 tons of structural steel joists, while approximately 150,000 cubic yards of earth had been excavated to make room for its basement and foundation. Those are some substantial numbers behind a familiar part of Edmontonβs skyline.
Source: Alberta Business Journal, October 1969.