10/09/2026
Hamilton council already approved a plan to redevelop Eastgate Square into nineteen towers with 4,325 homes. So why is the first phase, three 20-storey towers with almost 700 units, now sitting in front of the Ontario Land Tribunal?
The owners, Hammer GP, filed an appeal because the city hasn’t issued the site plan approvals needed to pull building permits. A key sticking point: Hamilton’s own transit agency, the HSR, hasn’t finalized how buses will move through the site. Metrolinx has already signed off on its piece for the future LRT terminus.
The city says there are more issues than just transit, but hasn’t detailed them publicly while talks continue. A case management conference is scheduled for October 20.
This is a good reminder for anyone tracking Hamilton development: council approval is the start of the process, not the finish line.
HSR HamiltonNews RealEstateHamilton