We’re thrilled to share a new construction milestone at LEVEL - East Building’s structural wood framing is now complete, with significant progress continuing across both the East and West buildings.
🔹East Building: Framing is now complete on all levels, with roofing underway. Work is progressing with plumbing, electrical, mechanical, and fire protection systems rough-in, along with window prep and installation.
🔹West Building: Framing is coming up above the ground and has advanced to Level 2.
🔹Parkade: Installation of plumbing systems and fire sprinkler piping is moving forward steadily with sani & sewer piping ready to connect to the offsite civil.
With every milestone, we’re one step closer to welcoming you home. Stay tuned for our next update as Level continues to take shape!