We have been delivering our successful CIF Bid for the Heating & Pipework Replacement Project for Grove Learning Trust at Peatmoor Community Primary School.
The failing heating system has now been removed in its entirety and replaced with a completely new heating installation.
The works have included:
• New insulated heating pipework
• New fan convectors
• New radiators, including low surface temperature radiators where required
• New boilers
• New pumps and control valves
• A new control system with local thermostats
• Adjustments to the cold-water supply pipework
• Fire stopping around pipework where it passes through walls
• Boxing-in of pipework within classrooms and other areas
The new system has also been zoned to allow areas used outside normal school hours to be heated separately when required.
A substantial upgrade to the school’s heating infrastructure, providing improved control, reliability, and flexibility across the building.