When the plant room is built first, things rarely go as planned. Read how we installed a 330 kVA standby generator in a Plaistow building despite a 2.7m-high access opening and no crane path — creative rigging, careful planning and skilled installation made it happen. Read the full case study: https://wix.to/bQyFrL4
On paper it was straightforward. A 330 kVA standby generator for a building in Plaistow, East London. Concrete structure already up. Dedicated generator room already formed. An opening into that room of 2.5 m wide by 2.5 m high. Simple, you would think.It was not.The generator room was not at ground...