06/08/2017
All the drainage is now complete, both external and internal. The brickwork is up to scaffold height, and not shown the patio doors removed and blocked up. Internally a new doorway has been made, double doors have been removed and blocked up and all the plaster from the walls in the kitchen removed. Oversite concrete has been layed, sleeper walls are in and the floor joists fitted. Next is the interal block work and scaffold. .