YNOT Timber Construction

YNOT Timber Construction Timber Building Construction in Essex from Design to Completion

Brick and block work today and some more digging out for levels and over site this week
21/09/2026

Brick and block work today and some more digging out for levels and over site this week

Spending the next couple of days putting tons of skirting board in, would be a lot easier if I hadn’t got to do this to ...
07/09/2026

Spending the next couple of days putting tons of skirting board in, would be a lot easier if I hadn’t got to do this to the ball because the Plaster and the walks have huge bulges in them! 🤦🏼‍♂️

05/09/2026

In need of wheels on the midget dance floor

Busy week at Firestone house. Full on plastering this week.. and a few extra patches filled in.
05/09/2026

Busy week at Firestone house. Full on plastering this week.. and a few extra patches filled in.

Back on site today at the YNOT launderette!! skylight install more framing for the roof tomorrow Plaster boarding starts...
24/08/2026

Back on site today at the YNOT launderette!! skylight install more framing for the roof tomorrow Plaster boarding starts again. Dot and dab on the walls.

Well, that’s the main part of the house ceiling completed now onto the master bedroom and ensuite. More frames to build ...
19/08/2026

Well, that’s the main part of the house ceiling completed now onto the master bedroom and ensuite. More frames to build angles to sort out cables to finish and extraction.. but that’s next week now two days off.

been a long hot week of cable running and more suspended ceiling fitting and plaster boarding with a beer at the end of ...
14/08/2026

been a long hot week of cable running and more suspended ceiling fitting and plaster boarding with a beer at the end of today as ran out of pepsi.! average temp inside the glass house was 30.7 deg.

Little bit of alteration last week. Bashing out a wall and rebuilding studs to create a separate shower room toilet and ...
05/08/2026

Little bit of alteration last week. Bashing out a wall and rebuilding studs to create a separate shower room toilet and utility room.

Quick pitstop at the beach hut again to install a couple of handy shelves. Next stop the ice cream shop. 🙂
27/07/2026

Quick pitstop at the beach hut again to install a couple of handy shelves. Next stop the ice cream shop. 🙂

15/07/2026