If you're thinking of having a new kitchen in the next twelve months, you might want to give this page a like or a follow.
Over the next ten working days, I'm going to do something that I doubt anyone has ever done before; I'm going to post daily updates on a kitchen, that we started this morning, in Dobcross.
We are laying ourselves wide open to scrutiny, and anybody is welcome to publicly ask questions as the job progresses.
The schedule is as follows -
Day one (today) kitchen out, ceiling down, floor coverings- up. All pictured, below.
Tomorrow- Tuesday. The electrician will come and do all his alterations and upgrades.
Wednesday will see the plumber do his alterations, which on this job, involves a slight relocation of the boiler to a more suitable location, and swapping a radiator for a plinth heater. I will then re-board the ceiling.
On Thursday, the plasterers will do their preparation for..
Friday, when the room will be completely re-plastered.
The kitchen will dry over the weekend, and will then be painted.
Next Monday (12th) the new kitchen will be delivered from Howdens at Oldham, and will take four days to fit.
This job has quartz worktops. HM Granite are booked to template next Wednesday, and will hopefully fit their tops on Thursday.
Next Friday I will lay the flooring, and finish off any other bits.
I always promise a two week turnaround, this is the first time I've ever done it publicly!
Daily updates will only be available on this page, because I'll get banned if I post on all the community pages, every day!
Thank you!