17/05/2026
Week 8 & 9 – The finishing stages are now well underway on this kitchen extension build 🚧
Over the last few weeks, painting has been completed throughout the new open-plan space, while floor preparation and self levelling have been carried out ready for the LVT flooring.
The electricians have also been back on site completing the second fix, including spotlights, sockets and external lighting ahead of the kitchen installation.
Outside, work has started on the new patio and entrance areas to complete the external finish.
We’re still waiting on the final pocket door system before the remaining joinery and kitchen installation can be completed later this month.
Follow along to see the final stages of the transformation.