Dynamic Property and Investments Limited

Dynamic Property and Investments Limited A UK property & Investment company, owning both rental properties of various types, as well as running an active FLIPPING business.

We add value to all our investments by carrying out complete ‘back to brick’ refurbs, before either letting or selling.

21/04/2026

Project Brynteg FINAL update, 21 April:
And here she is!! 🎊 Project Brynteg finished, snagged, and across the line 🏁. It was a big refurb this, increasing bedrooms, adding and en-suite, laying a driveway… but what a result… and now, straight on the market! 🎆 🇬🇧

Project Brynteg update, W/e 4th April:Happy Easter! 🐇🐣 As we enter the long Easter weekend, the house is truly in the fi...
04/04/2026

Project Brynteg update, W/e 4th April:
Happy Easter! 🐇🐣
As we enter the long Easter weekend, the house is truly in the final straight, with only a few items o/s: 📋

See a few pictures updating current status (look at those beautiful finishes), with the only significant work’s outstanding being:
- carpets throughout the first floor the next week, but everything has been nicely 🧹 and readied for installation
- LVT flooring throughout downstairs
- garden & outdoor ☀️ works - just some grass & planting 🌴 o/s
- snagging…. 📋The all important final quality step, before the 🔑 🔑 are handed over, and she goes on the market! 🏁
🇬🇧

Project Brynteg update, W/e 20 March.A short update just to showcase the works that have gone on outside, including:- ne...
22/03/2026

Project Brynteg update, W/e 20 March.
A short update just to showcase the works that have gone on outside, including:
- new underground piping
- Groundworks for the new driveway
- gravel layering
The inside is currently having:
- second fix electrics 💡
- second fix joinery, incl. a new handrail
- 2nd fix plumbing and fittings 🚽🛁
- subway tiling in the kitchen

Project Brynteg, W/e 13 March:Unlucky for some, but fortunately the Project update on 13th March was positive! 🎉 - All b...
15/03/2026

Project Brynteg, W/e 13 March:

Unlucky for some, but fortunately the Project update on 13th March was positive! 🎉
- All bathroom, kitchen, 2nd fix joinery & LVT delivered to site ✅and all elements of installation are in progress. ✅
- En-suite 🚿 installation complete
- Kitchen & Utility installed ✅
- LVT has been laid downstairs
- 2nd fix joinery at circa 80% complete 🚪

In the next week, the plan is:
- Final fix electrics ⚡️ and plumbing 🪠
- 2nd fix joinery throughout to be completed
- Final paint 🖌️ to be complete

The light 💡 at the end of the tunnel is burning bright, with only carpeting, snags, and the garden left after the upcoming week to achieve completion.
Keep watching as we close this project out! 🏁

Project BrynTeg update, W/e 6 March:This week there were deliveries galore! 📦 - Bathroom 🛁 and kitchen supplies arrived-...
11/03/2026

Project BrynTeg update, W/e 6 March:

This week there were deliveries galore! 📦
- Bathroom 🛁 and kitchen supplies arrived
- LVT flooring was delivered
- 2nd fix joinery has been delivered
And some construction 🚧 happened too:
- 1st fix waste 🚽 completed and bathrooms ready for install ✅
- All extractor fans have been cored out and prepared ✅
- Joinery install🚪has commenced ✅

We’re targeting completion by the end of March, with final snags being closed by then, and then she’s on the market!
🇬🇧

Project Brynteg update, 22 February:A short update this week just to ensure we’re keeping you up for date….After quite a...
22/02/2026

Project Brynteg update, 22 February:

A short update this week just to ensure we’re keeping you up for date….
After quite a task, the plaster is now completely dry🏁.
With rain ☔️ in the UK everyday so far this year, that was a delay!
- B&K internals ordered and on site 🛁 🚿
- ground floor leveled and drying, in preparation for new floor installation
- new window window 🪟 installed to replace the previous

We’re getting there, and look forward to the Swan 🦢 this project is going to be!

-

Project Brynteg Update, 6 February:- all plastering is 100% complete ✅- dehumidifiers have been mobilized to site to ass...
08/02/2026

Project Brynteg Update, 6 February:

- all plastering is 100% complete ✅
- dehumidifiers have been mobilized to site to assist with the drying process… quite a job in winter ❄️ ☔️
- site wide clean out carried out to remove debris & waste 🧹 ✅
- 1st coat of paint complete 🖌️ 🎨 🏠
As we look 👀 forward to the next week, the tasks to be completed are:
- drying out of plaster to continue
- second fix joinery to be completed 🔨
- bathroom layouts and supplies to be procured and moved to site. 🚽 🚿 🛀🏼
Exciting times in the life of the project!! Keep watching this space…
🇬🇧

Project Brynteg Update, 23 January:- Plaster at 90% and TBC within the next week 🏁 - Chimney removed, new roof tiles lai...
27/01/2026

Project Brynteg Update, 23 January:

- Plaster at 90% and TBC within the next week 🏁
- Chimney removed, new roof tiles laid at apex and new string on either side of apex 🏠
And we chose the fixtures & fittings🚰… thanks to you who weighed in with your preferences… you’ll see it all in a few weeks! ✅
🇬🇧

EMERGENCY POSTING! 🚨 ‼️ If you follow us, and our projects, Dynamic Property & Investments 🏡 needs your help to choose a...
22/01/2026

EMERGENCY POSTING! 🚨 ‼️
If you follow us, and our projects,
Dynamic Property & Investments 🏡 needs your help to choose a few of the finishes for our current project, BRYNTEG.
Please review the below, and let us know by listing the title of the finish, and YOUR preference.
We need to lock in soon:
A: Kitchen colour
B: floor colour
C: counter colour
D: bathroom tiles - Gold/Blue/Grey
E: Carpet choice

Project Brynteg update, 18 January 2026:Steaming into 2026, it seems like the work didn’t stop!! 🏃‍♂️ .Following on from...
18/01/2026

Project Brynteg update, 18 January 2026:
Steaming into 2026, it seems like the work didn’t stop!! 🏃‍♂️ .
Following on from the final update if 2025,
- all the boarding is now 100% complete ✅
- plaster is very well progressed, as is evident from the pics ✅
- the source of the moisture that was identified at the back end of last year has been Identified ☔️ … it’s the chimney and the roof around the chimney 😧… but we have a plan
- chimney will be removed 🔨 and the roof closed.
- New roof tiles to be installed on the apex and the lower 2 layers of tiles 🛖… and then we will enter the final stretch to completion! 🏁.
Keep watching 👀 as we move onto the 2nd fix joinery/ electrics, B&K and more into February! 📅
🇬🇧

Address

Epsom
London
KT190NH

Telephone

+447493739631

Website

Alerts

Be the first to know and let us send you an email when Dynamic Property and Investments Limited posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Dynamic Property and Investments Limited:

Share