15/03/2026
Project Brynteg, W/e 13 March:
Unlucky for some, but fortunately the Project update on 13th March was positive! ๐
- All bathroom, kitchen, 2nd fix joinery & LVT delivered to site โ
and all elements of installation are in progress. โ
- En-suite ๐ฟ installation complete
- Kitchen & Utility installed โ
- LVT has been laid downstairs
- 2nd fix joinery at circa 80% complete ๐ช
In the next week, the plan is:
- Final fix electrics โก๏ธ and plumbing ๐ช
- 2nd fix joinery throughout to be completed
- Final paint ๐๏ธ to be complete
The light ๐ก at the end of the tunnel is burning bright, with only carpeting, snags, and the garden left after the upcoming week to achieve completion.
Keep watching as we close this project out! ๐