Residence- Pankaj Ratnesh This page is for sharing the updates on the progress of my home at Bangalore.

21/02/2015
Gruha-Pravesh @ 16JAN2015
31/01/2015

Gruha-Pravesh @ 16JAN2015

Painting in Progress
26/12/2014

Painting in Progress

Internal Plastering Over.. External plastering in progress
04/10/2014

Internal Plastering Over.. External plastering in progress

First Floor masonary work in progress..
20/07/2014

First Floor masonary work in progress..

Ground Floor roof slab casting done today 28June14..
28/06/2014

Ground Floor roof slab casting done today 28June14..

Wall masonary upto lintel completed.. 10Jun14... lintel work planned for 13Jun14...
12/06/2014

Wall masonary upto lintel completed.. 10Jun14... lintel work planned for 13Jun14...

Earth-filling in-plinth in progress..29 May-01June 2014..
01/06/2014

Earth-filling in-plinth in progress..29 May-01June 2014..

Plinth Beams casting done on 25 May 14...Form removal in progress 26 May 14..
26/05/2014

Plinth Beams casting done on 25 May 14...Form removal in progress 26 May 14..

Plinth wall in progress- 19May14
19/05/2014

Plinth wall in progress- 19May14

Foundation pits back-filling done today 09 May 14.
09/05/2014

Foundation pits back-filling done today 09 May 14.