02/06/2023
IVY COUNTY Construction Updates
Tower B1 - water tank work,
Marble Flooring toilet, Marble flooring stair case or lobby, Wall Tile Work, Internal door frame 27th floor, Zypsum plaster work 27th floor complete.
Lift work and External paint work in progress.
Tower B2: Water Tank Work,
Marble Flooring toilet 27th floor, Marble flooring stair case 27th floor, Stair case Railing Work 27th floor, Wall Tile Work 27th floor, Internal Doors frame work 27th floor, Zypsum plaster 27th floor, External door and windows work, lift work complete
External Wall Paint and Balcony railing work in progress
Non tower structure work and Water proofing work complete, Landscape work in progress, Club 1st floor slab complete
Commercial - Excavation complete & upper basement slab 80% casting complete
Tower C1 : water tank work, Marble flooring toilet 27th floor, Marble flooring stair case or lobby area 27th floor, Wall tile work 27th floor, Stair case railing work 27th floor, Internal door frame work 27th floor, Zypsum plaster work 27th floor, External door frame or windows work, Lift work complete
Balcony railing work in progress
Tower C2: water tank work, Marble flooring toilet 27th floor, Stair case or lobby area flooring 27th floor, Wall tiles 27th floor, Internal door frame work, Zypsum plaster work, External doorframe and window work complete
Balcony railing work in progress
Tower A : structure work, Marble flooring toilet 17floor, Wall tile work 19th floor, Zypsum plaster work 25th floor, Internal door frame 25 floor, Stair case and lift lobby stone work 4th floor complete.