14/02/2017
>>PROGRESS REPORT (End January 2017)
- Earthwork and slope stabilisation and protection work at Phase 3 (Slope 1) completed.
- Earthwork and slope stabilisation and protection work at Phase 1 (Slope 2) is still on going.
- Piling Works
o Ph.1 & Ph.2 Building – 100%
o Ph.3 & Ph.4 Building – 52%
Phase 2
- Building Works
o Substructure
- Pile Cap
• Block B2 – 100%
• Block B1 – 100%
- Ground Floor Slab
• Block B2 – 100%
• Block B1 – 100%
- Superstructure
• Block B2 – 100 %
• Block B1 – 100 %
- Architectural Works
o Block B2 – 100 %
o Block B1 – 100 %
- Mechanical & Electrical Works
o Block B1 & B2 – 100 %
- Ancillary (Bin Centre, Genset Room, SESB Sub-station)
o Piling works – 100%
o Building work – 100 %
o M&E works – 100%
- STP
o Piling works – 100%
o Structure
- Foundation & Building works – 100 %
- M&E works – 100%
Phase 1
- Building Works
o Substructure – 95%
o Superstructure – 25%
Phase 3
- Building Works
o Substructure – 8%
o Superstructure – 0%