13/05/2026
Binastra Business Park @ Pulau Meranti 2 Site Update:
• Roof slab formwork and rebar casting is underway.
• Roof slab formwork casting is in progress.
• Facade casting is ongoing.
• Brickwork and skim coat for level 2 soffit roof slab is in progress.
• Level 2 to roof brickwork is underway.
• Internal plastering is ongoing.
• Internal and external painting works for TNB substation is in progress.
• Septic tank installation is underway.
• Current structural progress: 78.5% complete.
• Current architectural progress: 9.5% complete
• Current M&E progress: 19.0%
• Overall progress: 36.0% complete.