⚠️MATERIAL AND LABOUR EXTIMATE FOR THE 2 STOREY BUILDING ( SIX FLATS).
TO LEVELLING ( BEFORE FIRST FLOOR SLAB ONLY‼️
FOUNDATION TO DPC✅
🟩150 tonnes of chippings ( iron stone ,black.setraco). at #650,000 per 25 tonnes.............3,900,000
🟩15 trips of sharp sand at 100,000 per trip...........1,500,000
🟩20 trips of laterite at 70,000 per trip.........1,400,000
🟩3200 no's of sandcrete hollow 9 inches block ( company standard). at 500 per block.........1,600,000
🟩330 bags of Portland cement (BOA) at 9500 per bag...........3,135,000
🟩180 lengths of 12mm reinforcement bars( complete gauge) at 9,400 per length........1,692,000
🟩70 lengths of 16mm reinforcement bars ( complete gauge)at 16,100 per length...........1,127,000
🟩80 lengths of 8mm reinforcement bars at 3500 per length........280,000
🟩200 lengths of sawmill boards at 3200 per length............640,000
🟩150 lengths of 2x2x12 purlins at 800 per length........120,000
🟩50 kg of binding wire at 32,000 per 20kg...............80,000
🟩1½ bag of 3 inches nail at 35,000 per bag.................53,000
🟩5 bundles of 900mm peg at 3000 per bundle.............15,000.
🟩Logistics ........150,000
🟩Sub total.......15,692,000
✅LABOUR INCLUSIVE*
General labour from setting out to Dpc. Oversite concrete slab.....................3,700,000
👉Supervision.........200,000
TOTAL.......19,592,000✅✅✅
MATERIAL AND LABOUR EXTIMATE FROM DPC TO LEVELLING.( BEFORE FIRST FLOOR SLAB* )
DPC TO LEVELLING.
🟥35 tonnes of chippings ( iron stone ,black.setraco). at #650,000 per 25 tonnes.............1,000,000
🟥7 trips of sharp sand at 110,000 per trip...........770,000
🟥5400 no's of sandcrete hollow 9 inches block ( company standard). at 550 per block.........2,970,000
🟥155 bags of Portland cement (BOA) at 10200 per bag...........1,581,000
🟥100 lengths of 12mm reinforcement bars( complete gauge) at 9,400 per length........940,000
🟥99 lengths of 16mm reinforcement bars ( complete gauge)at 16,300 per length...........1,613,700
🟥80 lengths of 8mm reinforcement bars at 4100 per length........328,000
🟥210 lengths of sawmill boards at 3500 per length............735,000
🟥50 lengths of 2x2x12 purlins at 800 per length........40,000
🟥30 kg of binding wire at 32,000 per 20kg...............48,000
🟥1½ bag of 3 inches nail at 35,000 per bag.................53,000
🟥1 bag of 2 inches nail..............32,000
🟥20 lengths of 2x4x16 hardwood ( scaffholding) at 1800 per length......36,000
🟥Logistics ........150,000
👉Sub total........10,266,700
LABOUR INCLUSIVE*
⚠️General labour from dpc to lmfround floor levelling.( block laying, iron work, carpentry work, casting and handling...........1,800,000
🤷♂️ TOTAL.......12,066,700*
OVERALL = 31,658,700✅✅✅
NOTE: Building estimates are influenced by many factors that can raise or reduce the projected cost of a project. If you really want to know some of these Factors,.(See below)
Here are the major factors affecting building estimates:
1. Type of Building Project – Residential, commercial, industrial, or specialized structures all have different cost implications.
2. Size and Complexity – Larger and more complex designs demand higher costs and longer construction time.
3. Design & Specifications – Architectural style, quality of finishes, and level of detail influence material and labor requirements.
4. Location of the Project – Accessibility, distance from suppliers, transportation costs, and local economic conditions matter.
5. Material Costs – Availability, quality, brand, and fluctuations in market prices of cement, steel, wood, etc.
6. Labor Costs – Skilled and unskilled labor availability, wages, and productivity levels.
7. Site Conditions – Soil type, topography, drainage, and need for excavation or demolition.
8. Duration of Project – Longer projects may cost more due to inflation, labor turnover, and extended use of equipment.
9. Regulations & Approvals – Government policies, taxes, permits, and compliance with building codes.
10. Contractor’s Experience – Efficiency, reputation, and methods used by the builder.
11. Contingencies & Risks – Unforeseen events such as weather changes, strikes, or design modifications.
12. Technology & Equipment – Use of modern machinery or traditional methods can change costs and speed.
13. Market Conditions – Inflation, demand and supply of construction resources, and overall economy.
👉 In short: Design, location, materials, labor, site conditions, and market trends are the biggest cost drivers.
At AAKKONZULT, we also have very affordable Land's in and all around Imo State🟦Abia State🟦Ebonyi State🟦Enugu State🟦Anambra State🟦Port Harcourt🟦Abuja🟦Lagos and Ogun State.
Now that you know, would you want us to give you an Estimate for your Dream Project? (NOT FREE).