Expenses for building fence:
1. Digging of foundation: N11,000.00
2. 9 inches blocks - 400 units @ N140 :
N56,000.00
3. 6 inches blocks - 1,350 units @ N120 :
N162,000.00 4. Cements - 42 units @ 1800 : N75,600.00
5. Gravel - 1 unit @ N15,000.00 : N15,000.00
6. Sharp Sand - 2 units @ N15,000.00 :
N30,000.00
7. Mason : N83,700.00
8. Site Supervisor : N19,800.00 10. Miscellaneous: N5,200.00
Total : N458,300.00.
Please note that we are yet to complete the
building of the fence. Two additional coaches
shall be added much later as we suspended it
so as to roof the house.

30/12/2015

Expenses for casting concrete on the Kitchen
roof, digging and building of Sock-away are as
follows:
1. Digging: N25,000.00
2. Cement - 19 units @ N1,700 : N32,300.00
3. 9 inches blocks - 300 units @ N130 :N39,000.00
4. Stone (called kuza in local dialect) - 2 units
,000.00 : N18,000.00
5. Sharp sand - 1 unit @15,000.00 :
N15,000.00
6. Gravel - 1 unit @ N15,000.00 : N15,000.00 7. Wood and labour : N19,000.00
8. Iron rods and labour: N38,700.00
9. Mason : N37,000.00
10 Site Supervisor: N6,000.00
11. Miscellaneous expenses: N2,200.00
Total: N247,200

30/12/2015

The house is a 3 bedrooms all ensuite with the
master bedroom having dressing room. The
Kitchen also have a store.
Total of 3,635 blocks were used from
foundation to roofing level.9 inches blocks
were used for the foundation and the outer walls while 6 inches only used for the inner
walls.
Materials used and their cost from foundation
to roofing:
1. cost of digging the foundation is N35,000.00
2. 9 inches blocks - 2,200 units @ N130: total is N286,000.00
3. 6 inches blocks - 1,435 units @ N110: total
is N157,680.00
4. Cements - 132 @ N1700: total is
N224,400.00
5. Sharp sand - 6 @ N15,000: total is N90,000.00
6. Gravel - 4 ,000: total is N60,000.00
7. Literite - 11 @ N6,500: total is N71,500.00
8. iron rods, binding wire and labour :
N47,500.00
8. Woods, nails and labour : N126,600.00 9. Mason : N261,200.00
10. Site Supervisor: N42,400.00
11. Water : N14,250
12: Miscellaneous expenses: 39,000.00
Total expenses from foundation to roofing:
N1,455,530.00

30/12/2015

How many bags of cement do u ned to use for
Foundation footing ------
Foundation Wall ------
Ground floor slab ------
Blockwork ------ Lintels and roof beam ------
Wall Rendering (Plastering) ------
Dressing of Windows, doors, burglary and
other metal works ------
Floor and Wall Tilling ------
Electrical and Mechanical patching and fixtures ------ etc. (Like dis page 4 more info)

Address

Adjacent Ajumobi Medical Lab, Adeoyo Hospital Ring Road Ibadan
Saki

Telephone

+2348166552567

Website

Alerts

Be the first to know and let us send you an email when Mosaic Dynasty Realty Ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share