29/09/2020
September Update
We have had several purchasers enquire as to specific dates for settlement. We understand that there’s a lot to arrange in terms of terminating tenancies, funding approvals and valuations… the list goes on. It’s important to stress that we too have several things to arrange on our side – Titles (under review at LINZ currently so not far away from issuing. Estimated mid-October), Practical Completion Inspections and Code Compliance Certification – as well as all the other items such as soft landscaping, cleaning etc. So as there’s many variables needed to align so that we can provide a specific date, we thought we would share our estimated (tentative) settlement programme. Please note that this is a tentative programme only, and is dependent on external entities to complete certain aspects for settlement to occur.
October 23rd – 30th : Blocks A, C & F
October 30th – November 6th: Block B
November 20th – 27th: Blocks D, E, G & J
We are pushing to get Blocks H & I completed by the end of the year, however the current programme has them for completion in January 2021. The impacts of Covid-19 and subsequent lockdown has obviously forced a re-calibration to our build programmes.
There are a few purchasers who require an independent valuer to view their future property prior to bank funding being approved. Please contact us on [email protected] and we can arrange this to occur. Please note that we will only allow valuers access when we feel it is both safe from a construction perspective, and when the property is in a near or fully completed state so that best value is achieved for our purchasers. We only permit valuers access, not purchasers - sorry.
Blocks A & C have practical completion inspections booked for next week, followed by Block B the week after. Block F interiors are all painted, with kitchens now being installed as well. Progress elsewhere is going well – lining, plastering / painting, as well as the hard landscaping works too. We’re also formally setting up the Residents Society – ready for hand over at the completion of settlements.
We look forward to seeing those purchasers attending the ‘Ron Deal Way’ street sign unveiling at Central Park on Copeland at 2:30pm on the 29th October. An invitation has been sent out to each purchaser.
The UPLLP Team