10/10/2024
LOOK | The 17.8-KM Davao City Coastal Road—SEGMENT D | October 2024 Update
The segment D or the last segment of this 33-billion project is now set to be completed and passable by 2026. This will ease the traffic congestion in Downtown, Agdao, and Lanang Districts.
The project covers the construction of a 4-lane (15.40-meter road width), 10mm thick asphalt pavement with anti-rutting additive (ARA); the construction of bicycle lane; and the construction of curb, gutter, and sidewalk. The entire width of the road including the off-carriageway is 25.54 meters or almost equivalent to an 8-lane road.
Part of this multi-billion development are the 3 major bridges out of 17 bridges in total. These major bridges are as follows:
• 660 meters Talomo-Matina Bridge
• 803 meters Sta. Ana Bridge
• 1.34-kilometer Davao River (Bucana) Bridge worth ₱3.126 billion, which is poised to be the longest river bridge in Mindanao
📷 RPV moto travelvlog