Pinnacle Projects & Development Atara, our brand new development offers ultra modern living spaces, with breathtaking ocean views.

Final preparations are underway at Villa B5, with lighting tests being carried out to ensure all systems are functioning...
02/07/2026

Final preparations are underway at Villa B5, with lighting tests being carried out to ensure all systems are functioning correctly.

The kitchen is scheduled for installation next week, marking one of the final stages before handover. We’re looking forward to completing the remaining finishing touches and handing over another high-quality home.🏡😁🔑

Progress continues well on Kala Kiri villa project. We’ve recently completed a series of fascia and eaves design upgrade...
26/06/2026

Progress continues well on Kala Kiri villa project. We’ve recently completed a series of fascia and eaves design upgrades, creating a cleaner, more contemporary appearance while still maintaining the traditional architectural character of the home.

The lighter, modern colour palette has given the villa a fresh new look and significantly enhanced its overall street appeal.

Alongside these improvements, we’re continuing with the internal and external finishing works as we move closer to completion. ✅👷🏽‍♂️👌🏼🏡

Villa B5 is almost ready for handover, with only the final finishing touches and quality checks remaining.    Everything...
11/06/2026

Villa B5 is almost ready for handover, with only the final finishing touches and quality checks remaining.

Everything is coming together well, and the villa is looking great. 🏡👷🏽‍♂️✅

Villa A2 has now been successfully handed over to the client. We’re delighted with the finished result, and most importa...
08/06/2026

Villa A2 has now been successfully handed over to the client. We’re delighted with the finished result, and most importantly, the client is extremely happy with their new villa. Thank you to everyone involved for helping make the project a success. 🔑 🏡 🌴 😎

Maenam villa project is now back on track after a brief pause, with strong progress continuing across all areas. 📋✅😎🌴☀️C...
12/05/2026

Maenam villa project is now back on track after a brief pause, with strong progress continuing across all areas. 📋✅😎🌴☀️

Current works include finishing details, eaves and soffits installation, air conditioning works, skim coating, and painting as the project moves closer towards completion. 👷🏽‍♂️🔨🧱

One Bophut project continues to progress well, with the swimming pool and surrounding terraces now complete, including t...
25/04/2026

One Bophut project continues to progress well, with the swimming pool and surrounding terraces now complete, including the new concrete structure and sandwash floor beautifully finished.

Villa 3, the formation of new door and window openings has been successfully completed, and works are now moving into the next phase, including ceiling installation, skim coating, undercoat preparation, and tiling works.👷🏽‍♂️🧰🪚🛠️

Villa 9–10 at One Bophut are progressing well, with the main interior works now largely complete. The feature floating s...
16/03/2026

Villa 9–10 at One Bophut are progressing well, with the main interior works now largely complete. The feature floating staircase with glass balustrades has been installed, while flooring, wall finishes, and kitchen cabinetry are now in place. The villas are moving into the final stage of lighting, fittings, and finishing details ahead of handover. 👌🏼🔑🏠

One Bophut is progressing strongly, with Villas 9–10 now nearing handover. The pool terrace structure has been completed...
25/02/2026

One Bophut is progressing strongly, with Villas 9–10 now nearing handover.

The pool terrace structure has been completed, and works are moving forward onto the surrounding pathways as we enter the final stages.

Meanwhile, progress continues steadily on Villas 7–8, bringing the overall project closer to completion with each milestone achieved. ✅📋👷🏽‍♂️

Atara B5 is progressing well, with installation of the glass balustrades now underway, enhancing both the safety and the...
25/02/2026

Atara B5 is progressing well, with installation of the glass balustrades now underway, enhancing both the safety and the clean, modern aesthetic of the design.

At the same time, final stages of the swimming pool works are being completed.

The villa is steadily moving closer to completion as these key detailing elements come together.🌴😎🔑🏠

Atara A2– Final phase of rockwork installation, beng completed 🪨 😎 🏡
21/02/2026

Atara A2– Final phase of rockwork installation, beng completed 🪨 😎 🏡

ที่อยู่

Ko Samui
84330

เว็บไซต์

แจ้งเตือน

เป็นคนแรกที่รู้ข่าว: เราจะส่งอีเมลแจ้งเมื่อ Pinnacle Projects & Development โพสต์ข่าวสารและโปรโมชั่น อีเมลของคุณจะไม่ถูกนำไปใช้เพื่อวัตถุประสงค์อื่น และคุณสามารถยกเลิกการรับข่าวสารได้ทุกเมื่อ

ติดต่อ ธุรกิจของเรา

ส่งข้อความของคุณถึง Pinnacle Projects & Development:

ทางลัด

แชร์