🌿The overview of Layan Verde project updates. Sharing the construction progress by the end of July 2026:
Soil excavated and removed — 341,100 m³
Piles drilled — 2,289 piles
Structural concrete poured — 26,954 m³
Building A5: Masonry works continue on the 4th floor; plastering work is in progress on the 5th floor, with ceiling installation ongoing; MEP works are ongoing.
Building A4: Work on the stair structure continues.
Building A2.2, Zone 1: Reinforcement installation is in progress on the 3rd floor slab.
Building A2.2, Zone 2: Scaffolding installation is underway on the rooftop.
Building A3.1, Zone 1: Post‑tension systems are being installed on the 4th floor slab.
Building A3.2: Work continues on the basement structures.
Building BM1: Foundation works are ongoing.
Building BM2, Zone 2 (Basement 2): Vertical structural works continue.
Building A1: Foundation works, water tank construction, and underground MEP system installation are underway; a partial basement floor slab has been poured.
Building ME1: Foundation works and water tank construction continue.
Building B8: Work is ongoing on the basement floor slab and RC walls.
Building B9: Foundation works are in progress.
Building B1: Pile drilling continues