𝐌𝐚𝐯𝐢𝐬𝐭𝐨𝐧 𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬 𝐔𝐩𝐝𝐚𝐭𝐞 – 𝐉𝐚𝐧𝐮𝐚𝐫𝐲 𝟐𝟎𝟐𝟔
We are pleased to share with you the latest update on the progress of Maviston Mai Khao, developed by Mai Khao Golden Beach. Our team is working step by step to bring the project closer to completion, and we are delighted to keep you informed along the way.
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐉𝟏
* Structural construction (excluding swimming pool): nearing completion
* Architectural work: 65% completed
* MEP (Mechanical, Electrical & Plumbing): 65% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐉𝟐
* Structural construction (excluding swimming pool): nearing completion
* Architectural work: 38% completed
* MEP: 60% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟏
* Structural construction (excluding swimming pool): 15%
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟐
* Structural construction (excluding swimming pool): 50%
* MEP: 15% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟑
* Structural construction (excluding swimming pool): 80%
* MEP: 28% completed
Every completed stage brings us one step closer to welcoming you to the Maviston Mai Khao experience. We remain committed to delivering exceptional quality and maintaining steady progress throughout the construction process
Stay tuned for our next update — 𝐖𝐡𝐞𝐫𝐞 𝐭𝐡𝐞 𝐡𝐨𝐫𝐢𝐳𝐨𝐧 𝐛𝐞𝐜𝐨𝐦𝐞𝐬 𝐲𝐨𝐮𝐫 𝐡𝐨𝐦𝐞. 🌴✨
📱𝐖𝐡𝐚𝐭𝐬𝐀𝐩𝐩/𝐂𝐚𝐥𝐥: : 065 408 2777
🌐𝐖𝐞𝐛𝐬𝐢𝐭𝐞: https://maviston.com
📌𝐋𝐨𝐜𝐚𝐭𝐢𝐨𝐧 https://maps.app.goo.gl/bEfKuB3yAeSVyX1m6
*Terms and conditions apply.