🔹 Construction Update – The Eyes of Zanzibar | 24.07.2026 🔹
We’re pleased to share the latest construction update for The Eyes of Zanzibar. Throughout the past reporting period, steady progress has been achieved across all major construction areas, with several key milestones successfully completed while finishing works continue on schedule.
Project Highlights
🏗️ Block A
• Blockwork and parapet walls on the 7th floor have been fully completed.
• MEP works on the 7th floor have been completed.
• Plastering works on the 7th floor are currently in progress.
• Plastering and screed flooring in the technical room are actively progressing.
• Gypsum board installation on the 6th floor has been completed.
• Tile repairs and grout finishing have reached the 5th floor and are continuing.
• Plastering of flower walls throughout the building is progressing, with only the roof level remaining.
🏗️ Block B
• Construction of internal walls on the 7th floor is currently in progress.
• Parapet walls on the 7th floor have been completed.
• MEP works on the 7th floor are actively progressing.
• Concrete pouring for lintels on the 6th, 5th, and 4th floors is underway.
• Ground floor wall construction is progressing according to the architectural layout.
• Reinforcement and formwork for the new public staircases in the basement are in progress.
• Gypsum board installation around elevator shafts is progressing throughout the building.
• Plastering of flower walls across the building is continuing, with the roof level still pending.
🏢 Public Areas
• Structural works from the 1st floor up to the roof have been fully completed.
• MEP works have been completed.
• PVC wall cladding has been completed.
• Plastering works are currently in progress.
📈 Overall, the project continues to progress according to plan. Several construction phases have already been completed, while finishing and interior works remain the primary focus for the coming reporting period. Continued coordination, timely material supply, and close site supervision will support the successful completion of the remaining works.