ROAD CONSTRUCTION UPDATE:
Next Week(Aug. 12 - 16): (Paving & Topsoil)
- Monday – Wednesday: 2 layers of asphalt pavement will be placed on the roadway. Multi Use trail on west side of 3/66 will be paved. Parking lots and driveways connections will also be paved.
- Thursday – Friday: Topsoil will be placed in boulevards and center of roundabout. Pond grading and underdrains near the Chamber Building. Install remaining street light poles.
Major Phase 1 Items Remaining: (what to expect over the next 3 weeks)
- Asphalt Paving
- Topsoil
- Seeding, Plantings, & Turf Establishment
- Signs
- Pavement Markings
- Site Cleanup, Restoration, Traffic Control Removal
Phase 2 Construction Update: (Begins September 2nd)
1. Traffic Control plan on CSAH 3 between CSAH 66 and Ostlund Ave:
a. Road closed to through traffic. Businesses accessible at all times for local traffic. The Road grade is not changing significantly and will be passable for traffic.
b. Intersection of CSAH 3/37/Pioneer Dr open to traffic.
2. Traffic Control plan on CSAH 66 between Swann Dr and Bald Eagle Trial.
a. Road closed to through traffic. Businesses accessible at all times for local traffic using CSAH 66 (from north and south).
b. The Contractor will remove pavement on east side of CSAH 66, begin grading, and install storm sewer. Local traffic will utilize the west half of CSAH 66 to access businesses in the closure area.
c. Once the east side is graded, the contractor will remove pavement on the west side of CSAH 66, begin grading, and install storm sewer. Local traffic will utilize the east half of CSAH 66 to access businesses in the closure area.
REMINDER: The construction site/roundabout is NOT OPEN to thru traffic. Please continue to use the detour so that the heavy equipment operators can move around freely. 🚜