07/23/2026
It’s been another exciting stretch of progress across the project! Building A continues to move into the finish stage with drywall complete, Gypcrete installed, cabinets delivered, painting underway, waterproofed breezeways, and exterior stone and trim nearing completion. Building B has seen insulation completed, drywall installation and finishing progress, while Building C has passed both framing and MEP rough-in inspections and is ready to transition into the next phase of construction. Site improvements also continue with amenity foundations and light pole bases installed and transformer pad construction completed.
Looking ahead, crews will continue interior finishes with painting, Gypcrete pours, trim-out work, and drywall installation while framing of the amenity spaces gets underway. Building C will move into insulation and drywall, and site work will continue as utility infrastructure comes together. Despite frequent rain and extreme summer heat, the team has maintained strong momentum and remains on track for Building A turnover this fall, with the remaining buildings following shortly after.
Owner/Developer: Overland Property Group
Primary Funding and Allocation Agency: Tennessee Housing Development Agency
Pre-Development Loan: Bennington State Bank
Construction and Perm Loan: Capitol Federal
LITHC Investor: Midwest Housing Equity Group
General Contractor: MCP GROUP
Architect: Jones Gillam Renz Architects
Civil Engineer: Seaside Engineering and Surveying, LLC
Interior Designers: Collective Design Studios
Leasing and Property Management: Emerald Housing Management