05/10/2025
NEW CONSTRUCTION ADU PROJECT SERIES – PHASE 3: EXTERIOR & INFRASTRUCTURE
Big milestones are being hit as this vision takes shape! From the rooftop terrace coming together to the bathroom skylight filling the space with natural light, every detail is moving us closer to the finish line.
The essentials are locked in—mechanical, electrical, plumbing, and gas. We’ve leveled the landscape, polished the concrete floors for a sleek, minimal finish, welded the staircase, and installed the HVAC. It’s all coming together piece by piece!
Before diving inside, we focused on sealing the exterior with the roof, stucco prep, windows, and exterior sliding doors. These vital steps ensure the interior is “water tight” and ready for the next phase.
Coming up: the interior build-out begins!
Builder & General Contractor: Klacen Group Inc
Architect: Kevin Cendejas