South Main building

South Main building Remodeling progress of a 1906 commercial building into a home.

Rendering of what the kitchen may end up looking like. Stove and dishwasher aren’t where they may end up but general ide...
07/31/2026

Rendering of what the kitchen may end up looking like. Stove and dishwasher aren’t where they may end up but general idea.

Worked on clean out of the main floor. Ready to take down old lights and more tin. The goal is to place a fitness center...
07/22/2026

Worked on clean out of the main floor. Ready to take down old lights and more tin. The goal is to place a fitness center on the main floor until the skillet building is ready.

New roof and wall on the west side of the building. Within a few weeks we will foam coat the roof above the apartment. T...
07/14/2026

New roof and wall on the west side of the building. Within a few weeks we will foam coat the roof above the apartment. The electrician is working with the city to trench the line to the building and install two meters.

Progress on the back roof. They should lay down the TPO soon. Then we can finish off the inside wall which will be the k...
05/21/2026

Progress on the back roof. They should lay down the TPO soon. Then we can finish off the inside wall which will be the kitchen and bathroom. We had to support the upstairs floor so beams and supports were installed.

Starting to clean up the ceiling on the main floor. The roof needs tk be replaced. All this tin needs to come down. I’m ...
03/09/2026

Starting to clean up the ceiling on the main floor. The roof needs tk be replaced. All this tin needs to come down. I’m trying to save as much of the tin as I can to repurpose it.

The rendering the state approved except the tandom windows are optional.
02/14/2026

The rendering the state approved except the tandom windows are optional.

I sent in my rendering to the state of my proposal of the Dayton building on south main. He liked it and will take it to...
02/10/2026

I sent in my rendering to the state of my proposal of the Dayton building on south main. He liked it and will take it to his boss to sign the award letter. Briefly, the state will pay up to $100,000 to help fix my building.

There are also grants to help put a fitness center in a rural town so i will be applying for those as well.

Once that’s done, next year I can apply for a grant to help fix up my other Dayton building.

The bedroom and closet exterior walls are now framed and insulated. Progress.
02/06/2026

The bedroom and closet exterior walls are now framed and insulated. Progress.

02/04/2026
The new windows are installed upstairs.
01/03/2026

The new windows are installed upstairs.