02/02/2026
Last week at Grand View Heights, carport footings were poured and the carport frame and sheeting were set. Painting continued in Building B, allowing flooring to begin in painted units and the clubhouse. Appliances were installed in Building A units and the clubhouse, while electrical, plumbing, and HVAC trim-out continued in Building A. First-floor units in Building B were primed, electrical trim-out began in painted units, and trades continued punch work in Building A. Major milestones were reached with the fire final and TCO secured for Building A.
Looking ahead over the next three weeks, work will continue across both buildings with drywall, insulation, gypcrete, and tape and texture progressing alongside ongoing electrical, plumbing, and mechanical work. Exterior activities will ramp up with siding, stone, painting, sidewalks, and site features including the monument sign and trash enclosure. Interior finishes will continue with doors, flooring, and final trim, while site and carport coordination remains ongoing to keep the project moving toward completion.
Owner/Developer: Overland Property Group
Primary Funding & Allocation Agency: Wyoming Community Development Authority
Pre-Dev Loan: Midwest Housing Development Fund
Construction Loan: Bennington State Bank
Perm Loan: WCDA
LIHTC & Other Investors: MHEG
General Contractor: Overland Construction Group
Architects: Jones Gillam Renz Architects
Interior Design: Collective Design Studio
Leasing & Management Company: Asset Living