09/13/2022
Here is an updated virtual tour of the property about midway through the rehab. We still have some wallpaper to remove and painting to do. The windows on the front of the house are ordered and will be installed in a week or so. The den needs to be painted. The materials for the master bath are on order with a 5 week lead time. The upstairs bath still needs to be painted. The interior walls in the basement have yet to be installed. Once that is done we can install the shower in the basement then get the wiring done. the egress window is scheduled to go in to the basement on September 28th and 29th. The materials for the master shower are going to hold us up so we won't be done by October 1st. The gutters have yet to be repaired.
Virtual Tour by Jeff LeBeau