06/04/2026
It might take a little imagination, but this future Great Room will soon become the heart of the community. Future potlucks, holiday celebrations, social gatherings, card games, and conversations with neighbors will all happen right here.
Construction continues moving forward:
• Framing wraps up completely by the end of this week
• Painting begins on the 4th floor the week of June 8 and will work downward from there
• Exterior siding and stone veneer installation continue
• Parking lot utilities begin in mid-June, followed by curb work and the first lift of asphalt
Every week brings Oak Marsh another step closer to home!