6 mile Outpost

6 mile Outpost See you at the outpost! Your hometown retail center. Follow along as we build the future and share updates! Located adjacent to Buddy Boys

6 Mile Outpost Weekly UpdateThis week, crews have started working on the fire suppression system and running low voltage...
05/30/2026

6 Mile Outpost Weekly Update

This week, crews have started working on the fire suppression system and running low voltage conduits throughout the building.

Work is also continuing on the front of the building and patio area as those sections begin coming together. Behind the building, crews are digging for sewer and water lines as we prepare for the next phase, including pump installation and connecting the fire suppression sprinklers.

A lot of behind the scenes progress is happening right now as we continue moving forward step by step.

See you at the Outpost!

From the beginning to now.It’s been exciting to look back and see how much progress has been made over the last few mont...
05/16/2026

From the beginning to now.

It’s been exciting to look back and see how much progress has been made over the last few months. From clearing the site in January to getting the roof structure up in May, things have really started coming together piece by piece.

We appreciate everyone following along through each phase of the process and can’t wait to continue sharing the progress ahead.

See you at the Outpost!

05/15/2026

6 Mile Outpost Weekly Update

The roof is now completely dried in, and the front porch posts have officially been delivered. Crews have also begun connecting the patio trusses to the main structure.

You can now really start to see the full height of the building and how the front of the property is going to come together.

We’re looking forward to getting inside soon and moving into the next phase with interior framing and more detailed work throughout the building.

See you at the Outpost.

05/04/2026

6 Mile Outpost Weekly Update 4/27–5/1

The roof is now fully dried in, with the protective layer in place across the structure.

This week, crews are focused on leveling out the parking lot area and getting the porch beams installed so roofing can begin on the porch.

Steady progress as everything continues to come together.

See you at the Outpost!

Some additional photos from last week at the outpost!
04/25/2026

Some additional photos from last week at the outpost!

04/25/2026

6 Mile Outpost Weekly Update 4/20-4/25

Roof trusses are now fully up and installed, with the exception of the patio area where we are waiting on wood beams for the porch.

Plywood is currently being placed on the roof, and the protective layer that goes underneath the final roofing is being installed.

On the site side, both drain fields have been completed, grease lines are in, and excess dirt has been hauled away.

Things are moving along as the structure continues coming together piece by piece.

See you at the Outpost!

04/16/2026

6 Mile Outpost Weekly Update

Roof trusses are now going up as we move into the next phase of construction. Crews will be taking their time with this step to make sure everything is properly set and secured.

After this, we’ll move toward getting the roof on and the building fully enclosed.

Looking forward to seeing this next phase come together.

See you at the Outpost!

6 Mile Outpost Weekly Update 3/24–3/29Walls are now fully up, and crews are getting ready to begin setting the roof trus...
04/03/2026

6 Mile Outpost Weekly Update 3/24–3/29

Walls are now fully up, and crews are getting ready to begin setting the roof trusses.

Work is also underway on the drainage fields, and the outer property wall is nearing completion.

Looking forward to seeing the structure continue to come together in the next phase.

See you at the Outpost!

6 Mile Outpost – Weekly Update 3/24–3/29Walls are now fully up, and crews are getting ready to begin setting the roof tr...
04/03/2026

6 Mile Outpost – Weekly Update 3/24–3/29

Walls are now fully up, and crews are getting ready to begin setting the roof trusses.

Work is also underway on the drainage fields, and the outer property wall is nearing completion.

Looking forward to seeing the structure continue to come together in the next phase.

See you at the Outpost!

03/23/2026

6 Mile Outpost – Weekly Update 3/12-3/20

The slab has been poured, and walls are now going up on the north, south, and east sides. Framing on the front (west side) has also begun.

Over the next phase, the walls will continue to rise to their full height, and we’ll start getting ready for the roof trusses.

See you at the Outpost!

Address

8410 County Road 13 N
Saint Augustine, FL
32092

Alerts

Be the first to know and let us send you an email when 6 mile Outpost posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to 6 mile Outpost:

Share

Category