St. Paul Road Construction Update:
(May 12 – May 16)
Retaining wall prepping and forming of concrete footings and walls.
Concrete footings pour is scheduled for next week at the retaining wall next to the Donerly Parking Lot.
Crews will continue excavating and installing the new tree trenches on Minnesota Street south of 11th Street.
Please be aware of open excavations near walkways and don’t go beyond barriers.
Contractor plans to prep roadway for curb pour next Tuesday (5/13).
Contractor plans to continue prepping the roadway for concrete pavement at the end of the week on the east side of Minnesota Street from 10th Street to 11th Street.
Electrical Contractor (Kilmer) will be working at the 11th Street intersection next week.
Crews will be boring new conduits within the intersection and possibly preparing new signal pole foundations at the south corners.
Please be aware of the construction personnel and equipment as you travel through that intersection.
Contractor may have to close an additional lane on the north side of 11th Street during conduit installations.
Saint Paul Regional Water Services will be installing a temporary watermain connection down at the 9th Street intersection next week.
Construction schedules are weather and schedule permitting and subject to change.
If you are looking for information about current downtown road closures and construction impacts, please visit www.stpaul.gov/roadclosures.