🏗️ Construction Progress Update – Nobu Danang (July 2026)
Each component at Nobu Danang continues to be implemented in sync, from structural works and masonry to the MEP (Mechanical, Electrical, Plumbing) systems, steadily moving the project closer to completion.
📋 Breakthrough Plan for August 2026:
🧱 Structural Works:
Construction of floors 16–17
Preparing formwork, props, and working platforms for floor 18 and the swimming pool area
Building staircases for floors 5–6
🏢 Masonry & Finishing:
Continuing masonry from the basement up to floor 12
Waterproofing toilets and balconies
Applying primer and skimcoat in designated areas
⚡ MEP & Interior Fit‑out:
Installing MEP systems in the basement, podium, and tower blocks
Tendering and preparing for the model unit and interior fit‑out package
✨ Close coordination and fast‑paced construction progress are the strongest commitments from the Developer to valued Customers & Partners!