22/10/2026
Week 1 of Renovation
- Building Control Notices submitted
- Fire Risk Assessor
- Complete strip out of 3 kitchens, 3 bathrooms, all internal doors, skirting, architrave, panelling, laminate flooring & fireplaces
- Walls striped back to brick to 1m high for damp course
- Electrician and plumber marked walls for rewire and pipe tracking
- Tracking started and floors lifted
Very productive first week.