Wednesday Wisdom: Not all contingency is the same.
One of the easiest ways for project budgets to become confusing is to use the word “contingency” as though every contingency serves the same purpose.
It does not.
Contractor contingency typically sits inside the GMP and addresses agreed ex*****on risk.
Owner contingency sits outside the GMP and gives the owner capacity for owner-driven changes, evolving needs, or other retained risk.
Design contingency is generally a pre-GMP planning tool used while the design is still developing and exact pricing is not yet available.
Those are three different buckets with three different jobs.
When the lines between them are blurry, the project team can end up debating who owns a cost only after the cost has already occurred.
The better conversation happens earlier: What risk are we planning for, who owns it, and which bucket is actually supposed to pay for it?