09/04/2026
The momentum picked up this week, and we were able to complete the structural fills and soil compaction testing for all the footers for the pillars. Additionally, the keyways have been created for the retaining walls. Rebar installation and footer forming for the pillars are complete. For the keyways and retaining wall footers, work is planned for next week. Overall, this week's progress is significant. We also purchased a large amount of steel for the building, which is staged and ready to go. Xcel and core application reviews are complete and ready for buildout. A schedule from them will be published next week.