Tejas Ventures Inc

Tejas Ventures Inc Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Tejas Ventures Inc, Property developer, 17050 E Main Street, Parker, CO.

The momentum picked up this week, and we were able to complete the structural fills and soil compaction testing for all ...
09/04/2026

The momentum picked up this week, and we were able to complete the structural fills and soil compaction testing for all the footers for the pillars. Additionally, the keyways have been created for the retaining walls. Rebar installation and footer forming for the pillars are complete. For the keyways and retaining wall footers, work is planned for next week. Overall, this week's progress is significant. We also purchased a large amount of steel for the building, which is staged and ready to go. Xcel and core application reviews are complete and ready for buildout. A schedule from them will be published next week.

The rain continues to hinder us; we weren't able to make significant progress this week. To give you some insight, we ar...
08/29/2026

The rain continues to hinder us; we weren't able to make significant progress this week. To give you some insight, we are required to fill the holes with structural soil at the correct density and moisture, then compact it and test it. This process happens for every one-foot section to the top to ensure the ground's strength is reliable enough to support the foundation for the pillars. Due to the rain, we're not getting consistent results, and the engineers are hesitant to certify it with the foundation for the deck pillars, as it could pose safety risks. The team is doing their best to manage this situation. Other logistics related to Xcel for gas and Core for electric, including clearance paperwork, are complete for this week. We hope to pass the tests this week, and the concrete teams will then proceed with the next steps.

This week wasn't a good week; we couldn't make much progress due to the weather. The moisture in the ground prevented us...
08/21/2026

This week wasn't a good week; we couldn't make much progress due to the weather. The moisture in the ground prevented us from passing the moist test to backfill and also from setting up the pads that support the pillars for the patio. The holes we dug filled with water, and we had to drain them multiple times as it rained several times. I am hoping for a better week next week.

08/14/2026
Another week brought significant progress to our project. This week, we successfully completed the foundation work—remov...
08/14/2026

Another week brought significant progress to our project. This week, we successfully completed the foundation work—removing all casing, finishing insulation, and conducting concrete quality and break tests. Backfilling has commenced, filling the entire foundation with soil and ensuring proper compaction. We also finalized the steel purchase, including beams for the entire site, and completed the water installation.

08/07/2026

A lot of mommentum picked up with retail space construction. Things are progressing with some delays but we will catch up as we progress

Construction is underway with tremendous momentum, featuring pouring of concrete, installing rebar in stem walls, embedd...
08/07/2026

Construction is underway with tremendous momentum, featuring pouring of concrete, installing rebar in stem walls, embedding plates for structural support, and pulling water lines for utilities into the building.

This week has been slow with little progress. Everything was prepared for pouring the concrete with stem walls. However,...
07/31/2026

This week has been slow with little progress. Everything was prepared for pouring the concrete with stem walls. However, heavy rain on Wednesday caused water puddles on the site, resulting in the postponement of the concrete pour to next week. Utility and waterline work continue; they are working to extend to the west side. Next week, the plan is to pour the stem wall concrete, backfill soil into the foundation, and continue utility work. I added some structural drawings for your understanding.

Foundation casings are build with with rebaring. They will go thru the inspections and then pouring
07/21/2026

Foundation casings are build with with rebaring. They will go thru the inspections and then pouring

County water lines are being actively routed into the site and building, ensuring a reliable water supply.
07/21/2026

County water lines are being actively routed into the site and building, ensuring a reliable water supply.

Address

17050 E Main Street
Parker, CO
80134

Telephone

+17208417997

Website

Alerts

Be the first to know and let us send you an email when Tejas Ventures Inc posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Tejas Ventures Inc:

Shortcuts

Share