29/10/2026
This build will cost me around $150,000 in interest. Here's how I'm funding it (Part 4 of my dirt to $3M build in Sorell, Tasmania).
The whole project is about $1.8 million. My lender covers 70%, which is $1.26 million, and they don't hand it over on day one. They release it stage by stage as the build gets done. The other 30%, around $540k, comes from equity in my other properties.
A lot of people ask why I didn't go to a big bank. For a development like this, banks have tougher serviceability, lend smaller amounts and sometimes want presales. So I went to non-bank and second-tier lenders like La Trobe, Pepper, Liberty, Resimac and Firstmac.
It costs more though. The rate is 9.9% and the application fee is 1.5%, about $19,000 upfront. The interest is capitalised, so I don't pay it monthly. It gets added to the loan and I pay it when I sell. Good for cash flow, but it adds up to around $150,000.
The biggest lesson: once the loan is fully drawn, every month of delay costs about $10,000. That's why I always do the feasibility before I buy and keep a 10% contingency.
Would you go with a bank or a non-bank lender for your first development? Tell me in the comments 👇
Comment FUNDING and I'll send you my holding costs checklist.
Next Thursday: the entity I bought under and why it matters for tax.